PRESS RELEASE JCE Energy Ltd., a specialist in off-grid power solutions for hazardous areas, has been awarded the prestigious Inspiration…
JCE was appointed to design, manufacture and commission a fully ATEX & IECEx certified Temporary Power Supply Package to support critical subsea cable monitoring on the Okha offshore facility in Western Australia.
The system was engineered to maintain uninterrupted power to a specialist signal injection and insulation monitoring system during a 75 day period when the primary support vessel would be removed for scheduled maintenance.
The client required a self-contained, hazardous area compliant, DC power solution capable of sustaining continuous monitoring and active protection of subsea cables connected to a floating production system.
With the support vessel temporarily removed, no AC supply would be available. However, cable integrity needed to be preserved, monitored and actively protected to prevent insulation degradation or failure across ageing subsea infrastructure.
The solution needed to:
Due to the production critical and highly technical nature of the installation, specialist commissioning expertise was required to ensure safe integration with the monitoring system.
Harsh Offshore Environment
The installation location is exposed to severe offshore weather conditions, including high winds, salt spray, heavy rain and constant marine corrosion. Equipment therefore needed to be engineered for long-term reliability in an aggressive marine environment while remaining compact enough to fit within the limited available space on the structure.
To ensure durability and operational integrity, the system was designed with weather protected support frames and high ingress protection ratings, allowing it to withstand prolonged exposure to harsh offshore conditions.
Offshore Constraints
The system was installed on a floating production structure with limited deck space, restricted lifting access and no permanent accommodation facilities.
Personnel access was time critical, with a 5-7 day installation window.
No Available AC Power
During the 75 day vessel absence, no charging supply would be available. The battery system therefore had to be precisely sized to operate autonomously for the full monitoring period.
Logistical Complexity
Personnel were required to travel over 1,400 km north of Perth before helicopter transfer offshore. Installation and commissioning had to be completed efficiently before vessel disconnection.
JCE engineered and supplied a fully integrated Temporary Battery Power System comprising:
Battery Assemblies
Battery Isolation & Management
Charging Infrastructure
The batteries were carefully sized to sustain the full 75 day monitoring period without recharge. Once the vessel returned, chargers could be connected directly to the BMS for controlled recharge.
JCE also provided offshore pre-checks and commissioning support, working alongside the Viper specialist engineer to ensure safe installation and operational readiness.
The system remains installed for potential future use, demonstrating JCE’s capability to deliver robust, specialist offshore solutions under complex logistical and environmental constraints.
This performance was also formally recognised by project stakeholders:
JCE’s performance was recognised by project stakeholders, including Viper Innovations Ltd and Woodside Energy, highlighting the company’s commitment to delivering high quality engineered solutions under demanding conditions.
From specialist offshore battery systems to fully integrated hazardous area power solutions, JCE delivers engineered packages designed for reliability in the most demanding environments.
To discuss your next offshore or hazardous area power project, contact the JCE team.
Designing and delivering a custom solar power system for hazardous zones, enabling safe, off-grid energy in extreme conditions.
Supplying a bespoke solar power system for the South N'dola wellhead platform to support safe, reliable offshore energy.
Designing a custom level gauging system to enhance safety, accuracy, and operational efficiency at a gas bottling plant.